Cala Light & Space Flats STAS Amendment – List of Changes
Blocks DA3, DA4, DB3, DB4, DC2, DC3, DD2, DD3
- Render parge coat and dot & dab layer replaced by 25mm timber battens behind plasterboard in all stair cores. (WD1’s, WD2.2, WD2.3, WD6)
- Wall ties removed. Restraint ties added at floor levels in all cores. (WD2.2, WD2.3)
- Landlord store foundation wall positions adjusted to line through with changes listed above. (WD2.1) [DA3, DA4, DB3, DB4 only]
Specification (Section 2.2)
- Render parge coat and dot & dab layer replaced by 25mm timber battens behind plasterboard in all stair cores.
- Wall ties removed. Restraint ties added at floor levels in all cores.
Details (14, 15, 24, 25, 25.1, 25.2, 26, 27.2, 28.1, 32, 48.4, 50, 51, 51.5, 51.6, 80, 80.1, 80.3, 80.4)
- Render parge coat and dot & dab layer replaced by 25mm timber battens behind plasterboard in all stair cores.
- Wall ties removed. Restraint ties added at floor levels in all cores.
Amendments to:
STAS/22/052/DM110/SD; STAS/22/052/DM110/SS; STAS/22/052/DM110/11; STAS/22/052/DM110/12; STAS/22/052/DM110/13; STAS/22/052/DM110/14; STAS/22/052/DM110/15; STAS/22/052/DM110/16; STAS/22/052/DM110/17; STAS/22/052/DM110/18
STAS Application status
Approved
STAS Submission date
Council name
Application type
STAS Certificates